Upper Fintry, Shalal
Road, Valley of the Sun
Water System
Project Name:
Upper Fintry, Shalal
Road, Valley of the Sun
Water System
File Number:
5600-20-15
Start Date:
Under Design
Substantial Completion Date:
Fall 2011
Number of Units:
341 residential parcels
Project Cost: (estimated):
$5,936,000
Unit Cost:
Not to exceed $17,500 per
residential unit
Taxation/Unit/Year: Depends on interest rate at time of borrowing.
Based on 30 year
amortization:
- $1,200 per unit per year
(estimated)
Costs to Connect:
(based on today's rates
and subject to change)
- Application Fee: $200.00
- Building Permit Fee: $150.00 ($50.00 is refunded once connection
is approved)
- Water Meter:
$440.00
- Plus, all on-site costs to connect the existing residence to the service
connection at the property line are the responsibility of the owner.
Project Site Plan:
Project Boundary
Description:
-
To provide both domestic
water service with fire
flows to 341 residential
parcels in the service
area encompassing the
subdivisions of Upper
Fintry, Shalal Road and
Valley of the Sun.
Current Status:
-
January 23rd, 2012
- Project Status Update
The majority of the
project works have been
completed. Start-up,
testing and
commissioning of the
water system is underway.
These efforts are
expected to take
approximately 4 to 6
weeks to complete. This
completion schedule
could be compromised by
cold weather or if
problems are identified,
during start-up, that
need to be corrected.
It's likely that the
final costs of the
project will not be
established for another
few of months. Once the
final costs are
determined, property
owners will be notified
of the ‘per parcel’ cost
(not to exceed $17,500
per parcel) and also
notified regarding the
deadline date for a lump
sum payment.
Determination of the
final project costs will
not delay a property
owner’s ability to
connect to the new water
system, as long as the
connection, inspection
and water meter fees
have been paid.
However, service
connections cannot be
completed until property
owners are notified by
the RDCO that the system
is ready for use.
We thank everyone for
their patience and we
look forward to
delivering water to our
new customers within the
next couple of months.
-
November 24th -
Project Update Letter
-
October 3rd - 5th
- access closed to
Fintry Community Park
boat launch as part of
current phase of water
main installation.
-
September 23rd -
Project Update Letter
-
Friday, September
16th - crews are
installing the final
section of mains from
the Morden Road
pumphouse to Westside
Road.
Construction Notice
-
Friday, August 5th
- the Firwood Road
intersection with
Westside Road will be
temporarily closed while
construction crews tie
into the works at
Westside Road. A
temporary detour route
has been established and
signed. Please
follow signs and
instructions from crews
and flag people.
-
July 11th -
Letter sent to
property owners updating
construction.
-
June 27th -
Construction and paving
is complete along
Westside Road. For
approximately, four
week, crews will be
installing works in the
Valley of the Sun
subdivision.
Please watch for signage
and obey flag people on
roadways.
-
May 11th -
Construction Underway
News Release
-
May 6th -
Construction Schedule
(subject to change -
will be updated as
needed)
-
April 28th -
Project Construction
Update Letter for
Property Owners
-
April 8th Update-
the Regional Board has
approved the
construction contract
with Peters Brothers
Construction Ltd (View
Board Report) for
approximately 12-kilometers of watermains and two
pressure reducing
stations. Pending
contract signing and
final approval from the
Ministry of
Transportation and
Infrastructure, watermain construction
work will begin within
the next few weeks.
Residents are asked to
be aware that during the
construction phase,
there will be some traffic disruptions
and
we request for the
safety of workers and
residents that
patience and extreme
caution be used when entering
the active work zones.
Where alternate traffic
routes exist, please use these
alternate routes
whenever possible during
construction.
The
Morden Control Building
(the well site in Lower
Fintry) is beginning to
take shape with pouring
of the building floor.
We
are expecting that the
‘mid-level booster
station’ will be
tendered shortly,
with an anticipated
tender close in mid-May.
The booster station
should be under
construction by late May
or early June.
The
‘Firwood Road Storage
Reservoir’ will be the
last of the major
contracts and should be into
construction by early
summer.
Minor
electrical,
instrumentation and
communications work will
be the final component
of the project. These
are the works that will
be required to ensure
that all of the various
components of the
infrastructure can
communicate with each of
the other components.
These communications
works will also give the
Regional District the
ability to remotely
monitor the operation of
the new water system.
These final works will
commence in late summer
or early fall.
Subject to some
important approvals
being achieved, the
project is progressing
on schedule.
-
March Update - Environmental Services
Staff and
representatives from CTQ
Consulting Engineers
were on hand at a well
attended Open House held
at the Killiney Beach
Community Hall on March
12th, 2011.
The tendered design
drawings were available
for viewing at the
meeting, as were answers
to Frequently Asked
Questions. The
invitation to tender for
the Watermains and
Pressure Reducing
Stations closes on March
24th, 2011.
The Interior Health
Authority issued the
Waterworks Construction
Permit on March 7th,
2011 and residents can
expect construction to
commence in their
community this spring,
following Regional Board
approval of the contract
documents.
View
Open House Brochure,
Display Panel 1,
Display Panel 2 and
February
Open House Invitation Letter to Property
Owners and Residents
-
February Update - The
Regional Board awarded
the contract for
construction of the new
Control building, pumps
and wells to Maddocks
Construction Limited for
a price of $442,164.45
excluding HST.
View
Report to the Board
-
January 2011
Update - Detailed design work is
continuing on the
project. In January,
residents can expect to
see construction
activity at the Morden
Road Well Site. The
next phase of works at
Morden Road will be in
regard to placing pumps
into the wells and
capping off the top of
the wells to allow for
future connection to the
new water system. We
anticipate that
construction of the
Morden Road pumphouse
building will commence
in late February or
early March.
Construction of the
remainder of the water
system works is expected
to commence in late
March or early April.
Construction efforts,
which will be divided up
into several different
construction contracts,
will continue throughout
the summer and fall of
2011.
-
October 2010 Update -
- Detailed engineering
design work is
progressing on the water
system with attention
being given to the lower pumphouse design, on Morden Road. This
component of the project
has received a $400,000
grant from the Province
to assist with the
design and construction
of the new groundwater
wells, as well as the
pumphouse, at the Morden
Road site.
- The geotechnical
investigative work
within the existing
roadways has been
completed. The
geotechnical report is
currently being
finalized. This report
will be utilized by the
design consultant to
determine design
constraints (avoidance
of solid rock
excavation, for
example). The site
topographic survey is
approximately 80%
complete. The remainder
of the survey will be
completed once final
alignments have been
determined.
- It is expected that the
detailed design will
continue through the
winter months with
tender and construction
to commence in the
spring of 2011.
Construction completion
is anticipated for late
2011.
- July 16th
letter from CTQ
Consultants to affected
property owners.
- July 8, 2010 - the
Regional Board awarded
an engineering services
consulting management
contract to CTQ
Consultants Limited for
project administration
and administration of
the design, tendering
and construction of the
new water system.
Link to Report
-
Water Source
Identification and
Preliminary Water System
Design - May 2010
(28 pg 1.7MB)
-
Ground Water Development
Program Completion
Report - May 2010
(85 pg. 3MB)
-
Project Update Letter
- May 2010
- April 2010 - Request for
Statement of
Qualifications for
Engineering Services
tender process underway.
- April 14th
Information Meeting
Display Panel
- March 2010 -
notification of a Public Information
Meeting for Wednesday,
April 14th at Killiney
Beach Community Hall.
Updated information will
be available for
residents on this
project and several
other key topics.
View More Details.
- Design underway
- Part A - Engineering
Services contract
awarded to True
Consulting Group Inc. to
identify the preferred
water source(s) and
prepare the preliminary
project design..
Consultant:
- Engineering Services
- Construction Phase
CTQ Consultants Ltd.,
Garry Threlfall, CTech, Phone
(250) 979-1221 Fax
(250) 979-1232
Mobile (250) 212-3937
Email:
gthrelfall@ctqconsultants.ca
- Engineering Services
- Design Phase
True Consulting Group
Inc.
Contractor:
Peters Brothers
Construction Limited,
Pat Adkin, Phone: (250)
765-9601 Fax:
(250) 765-9603
Email:
pat@bcunderground.net
RDCO Contact:
Delphine Maja, Sr.
Engineering
Technologist, Phone: (250) 469-6262
Fax: (250) 762-7011
Email:
delphine.maja@cord.bc.ca
Background:
North Westside Water Service Feasibility Study
For more information or comment, please contact the Regional District
Development and Environmental
Services Department at 250-469-6241 or by email at
engineer@cord.bc.ca
|